| |
members with U bolts connections to the building
columns was fabricated in our Armidale workshop. A CWT
10000 collection well and custom two piece floor was
designed and constructed. The two piece floor was
required to overcome the 3500 maximum width road
transport restriction.
On site, the building was rigged. Multiple
adjustable lifting straps had to be used to ensure the
building did not distort and fail in the lifting
process. The building had to be braced with similar
straps in every plane. Once the masonry anchors were
removed, the building lifted off easily using a Franna
type crane.
Now the demolition, excavation and pad preparation
was done. The client required that the refurbished
building had a similar RL for the concrete floor as the
old building, and as close as possible to the original
building’s position. This required accurate site survey,
marking and pad preparation.
The collection well, footing columns and precast
floor were then placed by crane. A ground anchor system
ensured the collection well would not float once the
ground water established itself at its former level.
The building was now positioned and masonry
anchored.
Pureablue stainless steel pedestals were now fastened to
the ports cast in the concrete floor.
Backfilling and resurfacing of the surrounding
circulation space with washed gravel completed the
project. THE FUTURE:
CWT is kept abreast of upcoming toilet installations of this type, at remote non serviced sites, through the tender process.
Despite this sort of Jimmy Creek incident, toilet buildings using non compliant to AS1546.1 modified plastic septic tanks are still being designed and constructed. These systems will fail in the long term. The only solution is to demolish and start again.
Meanwhile, sensitive environments are at risk.
|
|