| (4200 kg and 1800 kg
respectively) from our Armidale factory, via Brisbane.
The collection wells were shipped as a combination, with
a temporary prop supporting the lid at mid tank. The six
tonne pack was trans-shipped from one truck to another
in Brisbane using a 10 tonne container forklift.
The CWT collection wells and all other building
components, including premixed aggregate and sand in
bulker bags were coordinated to be delivered and
consolidated at the Hamilton Island barge loading
facility at Shute Harbour.
A Franna crane was used to trans-ship the collection
wells from the truck and loaded with the building
materials on board the Lady Fraser barge in reverse
order to anticipate off loading at Whitsunday Island. A
24 tonne excavator was the brought on board.
Marine Parks staff had excavated the collection well
pits in the days prior to barge shipping. About an
hour’s steaming from Shute Harbour, the barge eased on
to the beach at high tide. The location is an idyllic
tropical bay on the lee side of Whitsunday Island, with
a narrow white beach edged by tropical forest. Waters
are a greeny blue over white coral sands. About a dozen
yachts and cruisers were moored in this paradise.
Urgent unloading of building materials was commenced,
with a tide conditions allowing only three hours window
to achieve two sites deliveries.
A rough terrain forklift was used to unload building
materials, whilst the excavator carried the collection
well across the beach and in to thick tropical woods and
placed in the leveled pit.
The lid followed, positioned and sealed. The excavator
and loader were then put back on to the barge, and the
barge relocated to the second site some 500 metres away.
Frantic works continued as the barge man needled
everyone to get done as he was “running out of water”
As soon as the loader and excavator were back on board,
the barge made a hurried exit to deeper waters.
This entire operation had taken six and half hours from
commencement of loading that morning. A remarkable
effort.
This operation has opened another opportunity for CWT
concrete collection wells. The Marine Parks Authorities
policy for non-flush toilet facilities is now to take
all human waste off site. Hence the sealed collection
wells. Pureablue will be working with the Authority to
develop management plans for the sites, in co- operation
with an accredited waste contractor. This waste
contractor will be briefed on the gear required for the
waste removal, seed water placement and general
operation of the systems. It is an essential part of the
system that seed water is placed in the collection well
at the commencement of each management cycle. The waste
is kept in suspension in liquid form, allowing the odour
management materials to interact with the waste, and
making the removal of the waste as a liquid an operation
that can be achieved easily in a remote location.
We see the next step in this style of installation is to
supply combinations of collection wells and precast
concrete floors. These floors will have all the
necessary inserts cast in to the concrete slab to attach
stainless steel post shoes to connect the prefab
building components onto the slab. This will eliminate
“site pouring of concrete” from the building
procedure...and simplify the whole construction time
table and effort. These precast floor components will
have less mass than the CWT 10000 collection wells, and
therefore present no added difficulty to the barge
shipping and on site handling procedures. |